Camden Wastewater Treatment Plant

The project included construction of a new wastewater treatment plant; consisting of new Influent Headworks / Screening & Grit removal facility, Fine & Coarse Bubble Aeration Basin; two (2) 80ft diameter Clarifiers; UV Disinfection / Effluent Facility, Sludge Handling & Blower Facilities, Maintenance Facility and state of the art Operations / Administration Building.

Contract Bid – $34.6 Million

Contract VE Value – $30 Million

Contract Duration – 26 Months

Completion – August 2014

Engineer – AECOM