Northwest Water Treatment Plant Improvements Phase II
Construction of a 23 MGD New High Service Pump Station that housed Five (5) 400 HP and One (1) 250 HP Vertical Turbine Pumps in pump cans, associated piping and valves and Electrcial Work. Filtration Improvements in Two (2) sets of Filters that included demolition of Existing Equipment, and installation of Equipment, Blowers & Air Scour Piping. New addition to the Existing Operations building to include a new lab area, office space and conference room.
Contract Value – $8.7 Million
Contract Duration – 15 Months
Completion – June 2016
Engineer – HDR Engineering