Upper Little Sugar Creek Replacement Sewer Phase 1

Removal of over 4000 LF of existing 12” clay gravity sewer main and replacement with new 18” PVC C900 and DIP in the same trench along with the removal and replacement of miscellaneous 8” gravity sewer mains, service laterals, connections, and replacing all existing sewer manholes. This project included the removal of over 500 CY of unsuitable trench soils and replacement with ABC stone. The project included the testing of all mains, vacuum testing all manholes, internal CCTV inspections of all new pipe, bypass pumping systems to maintain all existing sewer flows, clearing and grubbing r/w’s, dewatering, rock removal, and seeding and erosion control of all areas. In addition this project included traffic control, detours, and the milling and overlay of existing asphalt streets.

​Contract Amount – $1.3 Million

Contract Duration – 8 Months

Completion – April 2018

Engineer – Frazier Engineering